Construction: Aurora Corridor N 192nd to N 205th


 

Weekly Construction Update
Updated October 31, 2014

Utility Work

Excavation will continue during daytime hours (7:00 a.m. to 3:30 p.m.) for utility work (lighting and communications) on the west side of Aurora between N 200th Street and N 205th Street. Utility work will begin on the east side of Aurora between Echo Lake Place N and N 198th Street.

Roadway Work

Storm drain work, resulting in trenching and installation of pipes and inlets, is in progress. Over the next several weeks, construction of new curbs, gutters, and sidewalks will occur along N 199th and N 200th Streets. Retaining wall work will occur on N 195th and N 200th Streets. Both directions of Aurora and the affected side streets may be restricted to one lane during the daytime non-commute hours to perform any of the work above, weather permitting.

2014 Activities

Remaining activities on the west side of Aurora for this year include asphalt pavement removal, excavation, utility work, curbs, gutters, sidewalks, driveways, retaining walls, and paving. Utility work will occur on the east side of Aurora.

Construction_Safety_Poster Marked_ped_path PedestrianTrafficSign

Follow signs and footprints when walking near the construction zone.

 

Irrigation_installation Roadway_excavation

Irrigation installation 

Roadway excavation

Setting_new_light_poles
Setting new light poles

 

If you wish to receive project updates, please sign up for Alert Shoreline and select "Aurora Updates" as one of your community alert selections.

Links
Aurora N 165th - N 205th Page
Aurora 192 - 205 Design Map
Project fact sheet (Jan 2014)
Frequently Asked Questions
Shoreline Currents
Upcoming City events
Resources for businesses
Slide Shows:

Aurora_Project_Schedule_Timeline

Shop Shoreline Businesses