Construction: Aurora Corridor N 192nd to N 205th

Print


 

Weekly Construction Update
Updated November 21, 2014

 

No work will be performed over the Thanksgiving holiday weekend.


Utility Work

Excavation will continue during daytime hours (7:00 a.m. to 3:30 p.m.) for utility work (lighting and communications) on the west side of Aurora between N 200th Street and N 205th Street.

Roadway Work

Over the next several weeks, construction of new curbs, gutters, and sidewalks will occur along N 198th Street, N 199th Street, N 200th Street, and Aurora. Retaining wall work will continue on Firlands Way N, N 195th, and N 200th Streets. Landscaping work will also be taking place. Both directions of Aurora and the affected side streets may be restricted to one lane during the daytime non-commute hours to perform any of the work above, weather permitting.

 

Sidewalk_pour_on_N_200th Finishing_the_concrete_sidewalk_on_N_200th


Sidewalk pour on N 200th Street

Finishing the concrete sidewalk on N 200th Street 

Finished_sidewalk_on_N_199th
Finished sidewalk on N 199th Street

 

Construction_Safety_Poster Marked_ped_path PedestrianTrafficSign

Follow signs and footprints when walking near the construction zone.

 

If you wish to receive project updates, please sign up for Alert Shoreline and select "Aurora Updates" as one of your community alert selections.

Links
Aurora N 165th - N 205th Page
Aurora 192 - 205 Design Map
Project fact sheet (Jan 2014)
Frequently Asked Questions
Shoreline Currents
Upcoming City events
Resources for businesses
Slide Shows:

Aurora_Project_Schedule_Timeline

Shop Shoreline Businesses