Construction Update
Updated January 26, 2015 

Roadway Work

New curb, gutter, and sidewalk construction and irrigation/landscaping work will continue along Aurora between N 200th Street and north of N 205th Street. Concrete driveways will continue to be constructed on Aurora from N 198th Street north, including the side streets. Retaining wall work will continue on N 200th Street. Roadway excavation and grading will continue north of N 205th Street to SR-104. There will be work on the signals and street lighting at N 205th.

During this time, the southbound direction of Aurora and the affected side streets may be restricted to one lane during the daytime non-commute hours to perform any of the work above, weather permitting.

Utility Work

Seattle City Light, Comcast, and Frontier will continue installation of  their systems from N 192nd Street to N 200th Street. This work converts the utilities from aerial to underground lines.

Pre construction photo looking north near YMCA
Slope Grading April 2014
Roadway excavation May 2014
Graded BAT lane with sidewalk
December 2014 Almost There

View more of the work accomplished in 2014.

 

If you wish to receive project updates, please sign up for Alert Shoreline and select "Aurora Updates" as one of your community alert selections.

Links
Aurora N 165th - N 205th Page
Aurora 192 - 205 Design Map
Project fact sheet (Jan 2014)
Frequently Asked Questions
Shoreline Currents
Upcoming City events
Resources for businesses